Commissioning the Green Building

There is the potential for installation and operations problems in all newly constructed buildings. Green buildings may include special systems and equipment that are not familiar to the owner, maintenance staff, or some members of the design and construction team. Consulting an independent, qualified commissioning agent during the programming phase can save time and money and, perhaps most important, ensure that the building functions properly and is easy to maintain and operate as designed.

Commissioning is often thought of as a series of tests conducted on equipment prior to the turnover of systems to the building owner at the end of a construction project, but final testing of systems is only one aspect of commissioning a building. ASHRAE defines commissioning as the process of ensuring that systems are designed, installed, functionally tested, and capable of being operated and maintained to conform to the design intent. The process begins with planning and includes design, construction, start-up, acceptance, and training, and can be applied throughout the life of the building.

There are a number of commissioning resources available that employ different methods of accomplishing the same goal—providing a building that operates as intended—with full documentation and training on all systems. The sources that are referred to most often by owners and commissioning providers are:

  • Portland Energy Conservation Incorporated (PECI)
  • California Commissioning Guides (2006 available online for free)

    —New Buildings

    —Existing Buildings

  • California Commissioning Collaborative – Retrocommissioning Tool Kit (2007/2008 available online for free)
  • ASHRAE
  • Guideline 0-2005–The Commissioning Process
  • Guideline 1.1-2007–HVAC&R Technical Requirements for the Commissioning Process
  • Building Commissioning Association
  • Building Commissioning Handbook, 2nd Edition
  • SMACNA
  • HVAC Systems Commissioning Manual, 1st Ed., 1994
  • Not all aspects of each of these guidelines are required. Owners may choose to have the commissioning agent perform some of these activities and eliminate others. Not surprisingly, cost is the primary reason for reducing the commissioning scope, although it can be argued that the less thorough the commissioning, the higher the costs will be in change orders, energy consumption, and maintenance over the life of the building.

    LEED® 2009 for new construction and major renovations includes two levels of commissioning: fundamental and enhanced.

    These basic commissioning activities are prerequisites to achieving any rating:

  • Engage an independent Commissioning Authority (CxA) with documented experience on at least two projects. (For projects under 50,000 sq. ft., the CxA may be part of the design team.)
  • The CxA must report results directly to the owner.
  • The CxA is to collect and review the owner’s project requirements and basis of design documentation.
  • Develop and include commissioning requirements in the construction documents.
  • Develop and implement a commissioning plan.
  • Verify the installation and performance for each commissioned system.
  • Complete a summary commissioning report.
  • The commissioning process must be completed for the following energy-related systems:

  • Heating, ventilating, air conditioning and refrigeration systems, and associated controls
  • Lighting and daylighting controls
  • Domestic hot water systems
  • Renewable energy systems (e.g., wind, solar)
  • To receive two extra points for commissioning (enhanced commissioning), the following additional activities must be performed:

  • Prior to the construction documents phase, designate an independent CxA.
  • Conduct at least one focused review of the design prior to the mid-construction documents phase, and back-check the review comments in the subsequent design submission.
  • Conduct a selective review of contractor equipment submittal documents for equipment to be commissioned. Perform the review concurrently with the design engineer.
  • Develop a systems manual which provides future operating staff with the information required to understand and optimally operate the commissioned systems.
  • Verify that the training requirements for the project have been completed.
  • Review the operation of the building with operations staff within 10 months of substantial completion. Include a plan for resolving outstanding commissioning-related issues.
  • Consult the LEED Reference Guide for Green Building Design and Construction, 2009 edition for detailed guidance on the rigor expected for design and submittal reviews and creation of the systems manual.

    Commissioning tasks should be structured to meet the requirements of the project, and not just the points for a rating system. The more complex the components and systems, the more detailed the commissioning effort should be. For all projects that utilize the sustainable design approach, the commissioning agent should be hired during the programming phase so that he or she can provide input and help define what the building should and should not be able to do. In this way, attributes that may be deemed desirable by some may be negated by the commissioning agent prior to the design team spending any time incorporating these features into the design. Hiring the commissioning agent at this early stage of the process will provide the greatest benefit to the owner.

    Arthur Adler, PE, CEM, author of this article, is principal of Applied Energy Engineering & Commissioning located in Manchester, Massachusetts. This article is adapted from Green Building: Project Planning & Cost Estimating, 3rd Edition, available through RSMeans.

    Recent Comments




    Article Archive

    Date Article
    11/17/14 Top 10 largest construction project starts in the U.S. - October 2014
    11/14/14 Non-residential Construction Starts Rose Gently in October
    07/10/14 The Importance of Matching Volume to Contractor Capacity in JOC Procurement Strategy
    07/10/14 Consider a Seed Project as Part of Your JOC Procurement Strategy
    07/10/14 The Best Unit Price Book for Your Job Order Contract
    07/02/14 ECONOMIC NUGGETS – July 1, 2014
    10/23/14 Twenty major upcoming Water Treatment Plants and Manufacturing & Warehousing construction projects - U.S. - October 2014
    10/23/14 Twenty major upcoming Alberta and British Columbia construction projects - Canada - October 2014
    10/15/14 Trend lines of construction starts in Canada - September 2014
    10/15/14 Top 10 largest construction project starts in Canada - September 2014
    09/17/14 Twenty major upcoming midwest and northwest construction projects - U.S. - September 2014
    09/17/14 Twenty major upcoming medical and educational construction projects - Canada - September 2014
    09/17/14 Trend lines of construction starts in Canada - August 2014
    09/17/14 Top 10 largest construction project starts in Canada - August 2014
    08/15/14 Twenty major upcoming medical and educational construction projects - U.S. - August 2014
    08/15/14 Twenty major upcoming industrial and water treatment construction projects - Canada - July 2014
    08/15/14 Trend lines of construction starts in Canada - July 2014
    08/15/14 Top 10 largest construction project starts in Canada - July 2014
    07/24/14 Twenty major upcoming entertainment facility and stadium/arena construction projects - U.S. - July 2014
    07/24/14 Twenty major upcoming Ontario and Quebec construction projects - Canada - July 2014
    07/24/14 Trend lines of construction starts in Canada - June 2014
    07/24/14 Top 10 largest construction project starts in Canada - June 2014
    07/16/14
    07/14/14 Top 10 largest construction project starts in the U.S. - June 2014
    02/03/14 Infographic: Where Can You Use Project Leads in the Construction Process?
    07/25/13 The Canadian Economy’s Two Great Blessings
    02/15/13 Construction Economic Notes – February, 2013
    11/05/12 Recycled-Content Tile
    10/05/12 Fiber-Cement Siding
    09/18/12 Return on Your Green Home Improvement Investment
    08/09/12 Green Building Solutions to Stormwater Runoff
    08/07/12 An “Aha” Moment Solves Challenge of Cost Estimating Local Circus Roof
    07/19/12 Estimate Types
    06/20/12 Ground-Source Heat Pump
    05/14/12 Universal Design for Outdoor Living
    04/23/12 What Is Universal Design?
    04/09/12 Natural Landscaping
    03/14/12 Green Material Alternatives for Plumbing Fixtures
    03/02/12 Budgeting & Financing Green Construction
    02/22/12 Greening Your Firm
    02/10/12 Roofing Defects
    02/06/12 Roofs: energy efficiency strategies
    01/18/12 Commercial Real Estate and Green Construction
    12/14/11 Renewable Energy & Distributed Generation Technologies
    11/04/11 Tubular Skylights
    10/04/11 Are Online Ads An Endangered Species?
    09/27/11 Performance Bonds Guarantee Clients Receive Exceptional Service
    09/15/11 Deconstruction for Green and Economic Benefit
    09/01/11 4 Ways for Businesses to Create a Good First Impression on Twitter
    08/11/11 Building Information Modeling (BIM) for Green Building
    07/21/11 Green Alternatives for Concrete
    07/12/11 Evaluating Products Over Their Life Cycle
    06/30/11 Low-Cost Green Strategies
    06/28/11 Bricks are from Venus, Clicks are from Mars
    06/17/11 Zombie Avoidance Techniques for Building Product Manufacturers
    06/08/11 Blogs & Websites: The 5 Signs of Website Wellness
    06/06/11 Building Product Manufacturers & Green Products
    06/01/11 Is Fear of Sharing Information Costing Your Company Sales?
    05/26/11 What Are Green Products?
    05/20/11 The Building Envelope
    05/16/11 Blogging: Website Heal Thyself
    05/03/11 Metals Compared to Wood for Sustainable Construction
    04/12/11 Storm Water Collection & Infiltration
    03/23/11 Commissioning the Green Building
    02/23/11 Building Program for Green Design
    01/21/11 Building Deconstruction Process
    05/02/11 Why Building Product Manufacturers and Social Media Are a Marriage Made in Heaven
    05/06/11 Building Product Manufacturers: How Understanding Architects Can Help Your Business
    10/21/09 Distributors & Manufacturer Representatives
    07/15/10 Estimating Doors: Tips from the Experts
    07/06/10 How to Handle Construction Materials to Prevent Mold
    06/21/10 How to Maximize the Benefits of Exterior Security Lighting
    06/04/10 SmartBuilding Index
    06/01/10 Regional Housing Construction Tracking and Forecast Information
    05/28/10 How to Find Regional Construction Tracking and Forecast Information
    05/24/10 Building Product Manufacturers
    05/18/10 Practicing the Art of Sustainability - Why Atlanta's Current Building Codes Need Updating Now
    02/23/10 Learning to use EE
    01/11/10 Earn AIA CEU Credit Attending RCD Webcasts
    07/17/09 Cost Estimators Winning Work With BIM
    07/16/09 Becoming an Invited Bidder - More Tips
    07/16/09 Becoming an Invited Bidder - Tips
    07/16/09 Becoming an Invited Bidder
    07/16/09 SmartBIM Object Modeling Guidelines for Revit
    07/15/09 Interference Check and BIM
    06/26/09 A Look at Contractor Failure: Part 2
    06/19/09 RicciGreene Associates
    06/19/09 Doug Thornton AIA, LEED A.P. of AERC, PLLC
    06/18/09 A Look at Contractor Failure: Part 1
    06/12/09 Owners and SmartBIM Objects – What You Need To Do
    06/10/09 Dealing with the IRS
    06/05/09 Getting Paid on Construction Contracts
    06/02/09 BIM Coordination and Collaboration
    05/28/09 Marketing Your Construction Firm on the Cheap
    05/20/09 Little Habits with Big Payoffs for Contractors
    05/12/09 SmartBIM Spaces
    05/07/09 AIA Show Recap as Seen by the SmartBIM Solutions Team
    04/27/09 Business Case Study - Survey Of Spending Patterns In Educational Facilities
    04/23/09 Taking Advantage of the Recession: Hiring the Right People
    04/20/09 Cork as a Green Flooring Option
    04/08/09 Owners - It's Time to Substantially Increase Your Architect's and Engineer's Fees
    03/05/09 There's a Solution to Performing Time Consuming Quantity Take-Offs
    02/20/09 SmartBIM Library is Half-Off for a Limited Time Only
    02/09/09 You are Wasting Your Money
    01/20/09 Obama: 'Dramatic Action' On Economy Needed
    01/14/09 Use of BIM Jumps Dramatically Over Last 12 Months
    12/10/08 Minimizing the Size of Family Files (Revit Objects)
    11/11/08 Maximize Online Advertising Dollars
    11/07/08 Architects and Engineers, WE NEED YOU
    10/29/08 Why Do You Need SmartBIM Objects
    10/28/08 Why Building Information Modeling?
    10/29/08 10 Questions To Ask About BIM Objects
    10/08/08 The Object Mess
    10/07/08 Implementing BIM to Your Office
    10/06/08 Meeting the Needs for Governmental BIM Compliance while Avoiding Current Liability Obstacles
    09/15/08 The BIM Transformation is Manageable with the NEW SmartBIM Library v3
    09/14/08 KOLBE Windows and Doors vs. Building Information Modeling
    09/12/08 The Evolution of Building Information Modeling: BIM 1-2-3
    08/11/08 BIM 101 Overview - From Hand Drawings, CAD and now BIM
    08/12/08 Draper, Inc. on BIM Object Developments
    07/08/08 IFD Library Partners work to establish standards for creators of BIM software
    06/23/08 Architectural Education
    06/17/08 Parametric Revit Objects – Part I - Fundamentals
    06/17/08 Window Glazing Coefficients
    06/01/08 Frequently Asked Questions About Building Codes
    06/05/08 Calling All Current and Prospective Revit Users - This Blog Is For You
    05/06/08 System Requirements for SmartBIM Library
    05/06/08 SmartBIM Library 2.0 Release Notes
    05/05/08 Building Information Modeling Moves into AEC Mainstream, Adding Value to Project Delivery Process
    04/08/08 Flooring: Cost Considerations
    02/08/10 General Contractors & Trade Contractors
    01/24/08 Building Element Models (BEM)
    12/21/07 LEED Certification Primer
    12/13/07 Building Integrated Photovoltaics (BIPV)
    09/24/07 Mixed-mode Building Design Combines Old and New Ideas
    10/15/07 Checklists Identify Potential Envelope Design Improvements
    10/24/07 Greenroofs as High Performance Design
    10/21/07 What Makes a Building Product Green
    10/24/07 Lighting Considerations in Green Building
    10/24/07 Water Conservation in Green Buildings
    10/24/07 Rainwater Collection Systems
    10/24/07 Efficient Cooling Methods for Green Buildings
    10/24/07 Controlling Heat Transfer in Green Buildings
    10/24/07 Limiting Heat Loss Through Windows
    10/23/07 Formaldehyde Use in Building Construction
    10/23/07 Using Plants to Improve Indoor Air Quality
    11/05/07 Greening Healthcare
    10/19/07 Daylighting Controls
    10/19/07 Use of Windows, Skylights and Light Pipes in Daylighting
    10/19/07 An Overview of Daylighting
    10/19/07 An Overview of Solar Ventilation Air Heating
    10/19/07 Types of Collectors for Solar Water Heating
    10/19/07 An Overview of Solar Water Heating
    10/19/07 Cooling Load Advoidance
    10/19/07 Components of Passive Solar Heating Designs
    10/19/07 An Overview of Passive Solar Heating
    10/23/07 Improving Indoor Air Quality
    10/19/07 An Overview of The LEED Rating System
    10/19/07 Cost Considerations in Building Deconstruction
    10/17/07 Building Deconstruction
    10/25/07 Roofing Considerations in Green Building
    10/19/07 Green Site Selection and Development
    10/24/07 Reducing Energy Use in Buildings
    10/17/07 Green Demolition
    10/18/07 Integrating Solar Power Generation into Buildings using Thin Film PV
    09/10/07 Compost Company Promotes Green Environment
    03/31/06 Green Roof Sets An Example For Minneapolis Sustainable Design

    CMD Group- construction industry news-image” title=